We put great importance to data protection and therefore use the data you provide to us with upmost care. You can handle the data you provide to us in your personal dashboard. You will find our complete regulations on data protection and clarification of your rights in our privacy notice. By using the website and its offers and navigating further, you accept the regulations of our privacy notice and terms and conditions.

Accept

Challenge / Goal

The aim of the Parker project was to validate that series-produced electric vehicles (EVs) as part of a company fleet, can support the power grid with V2G services. Ultimately supporting the use of renewable energy whilst earning money through grid services. 

Solution

The project utilised a number of contemporary electric vehicles and V2G DC chargers provided by its industrial partners, and used them to carry out a number of tests and demonstrations in PowerLabDK - an experimental platform for power system research.
Further, the project partnered with the world’s first commercial pilot (the Frederiksberg Forsyning V2G hub) where electric vehicles provided grid services.
The project used the above assets to investigate three key topics: grid applications, grid readiness as well as scalability and replicability. 

Images


Want to learn more about the lessons learned, financial details and results?

Log in

Time period

Planning time: 6 months to 1 year

Implementation time: 6 months to 1 year

Implementers

DTU Elektro, NUVVE, Nissan, Insero, Frederiksberg Forsyning, Enel X, Groupe PSA, Mitsubishi Corporation, Mitsubishi Motors Corporation

Service providers

NUVVE

End users

The utility company Frederiksberg Forsyning

    Main benefits

  • Increasing share of renewables