We put great importance to data protection and therefore use the data you provide to us with upmost care. You can handle the data you provide to us in your personal dashboard. You will find our complete regulations on data protection and clarification of your rights in our privacy notice . By using the website and its offers and navigating further, you accept the regulations of our privacy notice and terms and conditions.

OK

Linked Projects

Challenge / Goal

The building in Lorystraße 54-60 was built from 1964-66 and since that only maintenance works were done. Hence, the thermal refurbishment was the first broad intervention since more than 50 years.

 

Solutions

Refurbishment and modernisation of energy supply
Lorystraße 54-60 (95 flats, 8.800 m²) is a city-owned social housing block, managed by Wiener Wohnen. The following technical improvements were planned:
▪ refurbishment of the building envelope from 125 to 52 kWh/m2 for space heating and warm water
▪ efficiency improvements to energy supply
▪ installation of PV plants of 7 kWp on the roof
▪ preparation of the parking garage for e-mobility
▪ ICT-based central management and monitoring of all buildings supplied by distance heating in the district

Refurbishment Concept
Therefore, a wide range of measures were necessary to adapt the building to nowadays standard.
▪ The refurbishment of the façade (exchange of windows, heat insulation), the roof and the basement ceiling reduce the calculated heat energy performance (HEP) from 125 kWh/m² to 52 kWh/m².
▪ The fire safety of the building is increased by a pressure aeration in all four staircases and doors in higher fire protection class to flats and community facilities (laundries, cellars, etc.).
▪ The modernisation/renewal of building equipment (elevators, plumping) increase energy performance and safety.
▪ The installation of a roofed waste collection place and an Intercom increase comfort for the tenants.

These standard measures, mainly concerning the reduction of the heat energy demand and the upgrade of the fire safety, were combined with additional measures dealing with the integration of renewable energy.
▪ The implementation of a 7 kWp PV-System at the roof
▪ The connection of additional flats to the DH
▪ Preparations for a future charging infrastructure for e-Cars and e-Bike

The construction works at Lorystraße 54-60 started in May 2018 with the erection of the scaffold and dismantling works (balconies, building equipment). In August 2018 refurbishment started with façade works (exchange of windows, installation of heat insulation), the insulation of the basement ceiling and works at the roof.

Citizen Participation

Citizen engagement and improvement of the neighbourhood plays an important role in the project. ▪ Wiener Wohnen as building owner together with the municipal department for architecture and city design worked out three different colour concepts for the façade. The tenants voted their favourite concept and decided upon it. ▪ Planned improvements in the park vis á vis Lorystraße 54-60 should developed together with the tenants

Want to learn more about the lessons learned, financial details and results?

Log in

Time Period

Planing Time:

Implementation Time: 0.5 - 1 years

Wiener Wohnen, Wohnpartner

Service Providers

Wiener Wohnen

End User

Tenants (263 Inhabitants in 95 flats)

    Main Benefits

  • Decreasing energy consumption in buildings,

  • Reducing energy bills,

  • Increasing share of renewables,

  • Improving life quality,